OF WEEK |
|
I |
II |
| Before ad publication | Prepare bids for mail out (written, printed, ready for delivery) ** | Regular | With Bid Conf | |
| 3 business days before
publication |
Wed before publication | FAX AD to newspapers | May 13,
Wednesday |
April 29,
Wednesday |
| 1 day | Monday after faxing ad | PUBLISH AD | May 18, Mon. | May 4, Mon. |
| 1-2 wks after publication | Tuesday | PRE-BID CONFERENCE** | N/A | May 19, Tues |
| 10 days prior to bid opening | Friday | PROTEST DEADLINE for bid specifications | May 22, Friday | May 22, Friday |
| Preferably 2 weeks after
pre-bid conference or advertisement |
1st Tuesday of month except
April, Oct, July (last Tues of previous month) |
BID OPENING and
Evaluation of Bid ** |
June 2, Tues. | June 2, Tues |
| Deadline:
Noon of Wednesday before Board meeting |
Tuesday | AGENDA ITEM DUE
(justification for board) ** |
June 10, Wed. | June 10, Wed |
| 3rd Wednesday of month | Wednesday | BOARD MEETING--AWARD | June 17, Wed. | June 17, Wed |
| Day after Board meeting | Thursday | PO, letter of award sent | June 18, Thurs. | June 18, Thurs |
| 7 days after award | Wednesday or Thurs | BID PROTEST deadline | June 24, Wed. | June 24, Wed. |
| Day after protest period | Thursday | BEGIN WORK if required forms received ** | June 25, Thurs. | June 25, Thurs. |
Conclusion: Please allow 6 weeks for the regular bid process from time of faxing ad to earliest date to begin work. Add approximately two weeks if a bid conference is involved. ** Department usually involved.
F:\GROUPS\BUSOFF\Bus_web\timechrt.wpd1998