TIME LINE FOR BIDS (ITB or RFP) (PURCHASES OVER $25,000)

 



 
TIME NEEDED
PREFERRED DAY

OF WEEK

ACTIVITY
EXAMPLE

I

EXAMPLE

II

Before ad publication Prepare bids for mail out (written, printed, ready for delivery) ** Regular With Bid Conf
3 business days before 

publication

Wed before publication FAX AD to newspapers May 13,  

Wednesday

April 29,  

Wednesday

1 day Monday after faxing ad PUBLISH AD May 18, Mon. May 4, Mon.
1-2 wks after publication Tuesday PRE-BID CONFERENCE** N/A May 19, Tues
10 days prior to bid opening Friday PROTEST DEADLINE for bid specifications May 22, Friday May 22, Friday
Preferably 2 weeks after 

pre-bid conference or advertisement

1st Tuesday of month except 

April, Oct, July (last Tues of 

previous month)

BID OPENING and 

Evaluation of Bid **

June 2, Tues. June 2, Tues
Deadline: 

Noon of Wednesday before Board meeting

Tuesday AGENDA ITEM DUE

(justification for board) **

June 10, Wed. June 10, Wed
3rd Wednesday of month Wednesday BOARD MEETING--AWARD June 17, Wed. June 17, Wed
Day after Board meeting Thursday PO, letter of award sent June 18, Thurs. June 18, Thurs
7 days after award Wednesday or Thurs BID PROTEST deadline June 24, Wed. June 24, Wed.
Day after protest period Thursday BEGIN WORK if required forms received ** June 25, Thurs. June 25, Thurs.

Conclusion: Please allow 6 weeks for the regular bid process from time of faxing ad to earliest date to begin work. Add approximately two weeks if a bid conference is involved. ** Department usually involved.

F:\GROUPS\BUSOFF\Bus_web\timechrt.wpd1998